Schedules

PIPE CASTING BUILDING 2 and BUILDING 3

BEGINS May 21, 2018 – August 24, 2018

Building 2 – 5/12/18 to 6/29/18

Building 2 Units Week of
2401, 2301, 2201, 2101
2402, 2302, 2202, 2102
2403, 2303, 2203, 2103
2404, 2304, 2204, 2104
5/21/18 – 5/25/18  8am
2405, 2305, 2205, 2105
2406, 2306, 2206, 2106
2407, 2307, 2207, 2107
2408, 2308, 2208, 2108
5/28/18 – 6/01/18  8am
Working Memorial Day
2409, 2309, 2209, 2109
2410, 2310, 2210, 2110
2411, 2311, 2211, 2111
2412, 2312, 2212, 2112
6/04/18 – 6/08/18  8am
2413, 2313, 2213, 2113
2414, 2314, 2214, 2114
2415, 2315, 2215, 2115
2416, 2316, 2216, 2116
6/11/18 – 6/15/18  8am
2417, 2317, 2217, 2117
2418, 2318, 2218, 2118
2419, 2319, 2219, 2119
2420, 2320, 2220, 2120
6/18/18 – 6/22/18  8am
2421, 2321, 2221, 2121
2422, 2322, 2222, 2122
2423, 2323, 2223, 2123
2424, 2324, 2224, 2124
6/25/18 – 6/29/18  8am

Building 3 – 7/9/18 to 8/10/18

3409, 3309, 3209, 3109
3410, 3310, 3210, 3110
3411, 3311, 3211, 3111
3412, 3312, 3212, 3112

7/9/18 – 7/13/18 8am
Stacks 109, 110, 111, 112

3413, 3313, 3213, 3113
3414, 3314, 3214, 3114
3415, 3315, 3215, 3115
3416, 3316, 3216, 3116

7/16/18 – 7/20/18  8am
Stacks 113, 114, 115, 116

3401, 3301, 3201, 3101
3402, 3302, 3202, 3102
3403, 3303, 3203, 3103
3404, 3304, 3204, 3104

7/23/18 – 7/27/18  8am
Stacks 101, 102, 103, 104

3405, 3305, 3205, 3105
3406, 3306, 3206, 3106
3407, 3307, 3207, 3107
3408, 3308, 3208, 3108

8/6/18 – 8/10/18  8am
Stacks 105, 106, 107, 108

3417, 3317, 3217, 3117
3418, 3318, 3218, 3118
3419, 3319, 3219, 3119
3420, 3320, 3220, 3120

8/13/18 – 8/17/18  8am
Stacks 117, 118, 119, 120

3421, 3321, 3221, 3121
3422, 3322, 3222, 3122

8/20/18 – 8/24/18  8am

Attention Owners

  • 4 stacks will be worked on at the same time
  • Schedule is established and cannot be negotiated
  • Owners, guests, LT Tenants – NO Occupancy
  • Notification will be posted on our website
  • Work will take 5 days and no unit can be occupied
  • Water off, pipes disconnected during 5-day period
  • No water can be in lines due to disconnections
  • Owners and Agents reminded the week before

click to view printable version

PIPE SCHEDULE = 24 STACKS = BUILDING 1 COMPLETED

BEGINS JUNE 19, 2017 – ENDS 10/20/17

Stack / Unit #’s Involved Work Days
1401, 1301, 1201, 1101
1402, 1302, 1202, 1102
6/19/17 – 6/23/17
6/19/17 – 6/23/17
1403, 1303, 1203, 1103
1404, 1304, 1204, 1104
6/26/17 – 6/30/17
6/26/17 – 6/30/17
1405, 1305, 1205, 1105
1406, 1306, 1206, 1106
7/10/17 – 7/14/17   8am
7/10/17 – 7/14/17   8am
1407, 1307, 1207, 1107
1408, 1308, 1208, 1108
7/17/17 – 7/22/17   8am
7/17/17 – 7/22/17   8am
1409, 1309, 1209, 1109 completed
1410, 1310, 1210, 1110
1411, 1311, 1211, 1111
8/7/17 – 8/11/17    8am
8/7/17 – 8/11/17    8am
1412, 1312, 1212, 1112
1413, 1313, 1213, 1113
8/14/17 – 8/18/17 8am
8/14/17 – 8/18/17 8am
1414, 1314, 1214, 1114
1415, 1315, 1215, 1115
9/11/17 – 9/15/17  8am
9/11/17 – 9/15/17  8am
1416, 1316, 1216, 1116
1417, 1317, 1217, 1117
9/18/17 – 9/22/17  8am
9/18/17 – 9/22/17  8am
1418, 1318, 1218, 1118
1419, 1319, 1219, 1119
9/25/17 – 9/29/17  8am
9/25/17 – 9/29/17  8am
1420, 1320, 1220, 1120
1421, 1321, 1221, 1121
10/2/17 – 10/6/17 8am
10/2/17 – 10/6/17 8am
1422, 1322, 1222, 1122
1423, 1323, 1223, 1123
10/9/17 – 10/13/17 8am
10/9/17 – 10/13/17 8am
1424, 1324, 1224, 1124
1425, 1325, 1225, 1125
10/16/17 – 10/20/17 8am
10/16/17 – 10/20/17 8am

Attention Owners

  • 2 stacks will be worked on at the same time
  • Work will take 5 days – no unit can be occupied
  • The schedule has been established and cannot be negotiated.
  • Water will be off starting at 8am the 1st day until 5pm the last day – unless you are notified.
  • Owners, guests, LT Tenants, etc. will have to be out of the unit during those 5 days.
  • No water can be in the line once work begins with causing delays and extra expense.
  • Notification of the schedule will be posted on our website.
  • All owners and agents will be contacted about the dates scheduled.

click to view printable version