Paint Schedule: 2014
April 7, 2014
1st Week 4/7: 3401 – 3406
2nd Week 4/14: 3407 – 3413
3rd Week 4/21: 3414 – 3418
4th Week 4/28: 3419 – 3422
May 7, 2014
Will take a month and move through the building as follows:
1st Week 5/5: 3401 – 3406
2nd Week 5/12: 3407 – 3413
3rd Week 5/19: 3414 – 3418
4th Week 5/26: 3419 – 3422
June 7, 2014
Will begin at 3401 – Exterior all around, Then work will be done in halls, entryways and doors:
1st Week 6/7: 3401 – 3406
2nd Week 6/14: 3407 – 3413
3rd Week 6/21: 3414 – 3418
4th Week 6/28: 3419 – 3422June 2, 2014 – July 31, 2014
Painting begins and will continue until completed. Estimated completion is July 31, 2014Exterior Building starting at South End of 3401:
Halls and Walkways
Individual Doors
We apologize in advance to all guests and owners for any inconvenience this causes during your vacation. We ask that you use caution in work areas. Your safety is essential for a successful project.