PIPE SCHEDULE = 24 STACKS = BUILDING 1 COMPLETED
BEGINS JUNE 19, 2017 – ENDS 10/20/17
Stack / Unit #’s Involved | Work Days |
1401, 1301, 1201, 1101 1402, 1302, 1202, 1102 |
6/19/17 – 6/23/17 6/19/17 – 6/23/17 |
1403, 1303, 1203, 1103 1404, 1304, 1204, 1104 |
6/26/17 – 6/30/17 6/26/17 – 6/30/17 |
1405, 1305, 1205, 1105 1406, 1306, 1206, 1106 |
7/10/17 – 7/14/17 8am 7/10/17 – 7/14/17 8am |
1407, 1307, 1207, 1107 1408, 1308, 1208, 1108 |
7/17/17 – 7/22/17 8am 7/17/17 – 7/22/17 8am |
1409, 1309, 1209, 1109 | completed |
1410, 1310, 1210, 1110 1411, 1311, 1211, 1111 |
8/7/17 – 8/11/17 8am 8/7/17 – 8/11/17 8am |
1412, 1312, 1212, 1112 1413, 1313, 1213, 1113 |
8/14/17 – 8/18/17 8am 8/14/17 – 8/18/17 8am |
1414, 1314, 1214, 1114 1415, 1315, 1215, 1115 |
9/11/17 – 9/15/17 8am 9/11/17 – 9/15/17 8am |
1416, 1316, 1216, 1116 1417, 1317, 1217, 1117 |
9/18/17 – 9/22/17 8am 9/18/17 – 9/22/17 8am |
1418, 1318, 1218, 1118 1419, 1319, 1219, 1119 |
9/25/17 – 9/29/17 8am 9/25/17 – 9/29/17 8am |
1420, 1320, 1220, 1120 1421, 1321, 1221, 1121 |
10/2/17 – 10/6/17 8am 10/2/17 – 10/6/17 8am |
1422, 1322, 1222, 1122 1423, 1323, 1223, 1123 |
10/9/17 – 10/13/17 8am 10/9/17 – 10/13/17 8am |
1424, 1324, 1224, 1124 1425, 1325, 1225, 1125 |
10/16/17 – 10/20/17 8am 10/16/17 – 10/20/17 8am |
Attention Owners
- 2 stacks will be worked on at the same time
- Work will take 5 days – no unit can be occupied
- The schedule has been established and cannot be negotiated.
- Water will be off starting at 8am the 1st day until 5pm the last day – unless you are notified.
- Owners, guests, LT Tenants, etc. will have to be out of the unit during those 5 days.
- No water can be in the line once work begins with causing delays and extra expense.
- Notification of the schedule will be posted on our website.
- All owners and agents will be contacted about the dates scheduled.