PIPE CASTING BUILDING 2 and BUILDING 3
BEGINS May 21, 2018 – August 24, 2018
Building 2 – 5/12/18 to 6/29/18
Building 2 Units | Week of |
2401, 2301, 2201, 2101 2402, 2302, 2202, 2102 2403, 2303, 2203, 2103 2404, 2304, 2204, 2104 |
5/21/18 – 5/25/18 8am |
2405, 2305, 2205, 2105 2406, 2306, 2206, 2106 2407, 2307, 2207, 2107 2408, 2308, 2208, 2108 |
5/28/18 – 6/01/18 8am Working Memorial Day |
2409, 2309, 2209, 2109 2410, 2310, 2210, 2110 2411, 2311, 2211, 2111 2412, 2312, 2212, 2112 |
6/04/18 – 6/08/18 8am |
2413, 2313, 2213, 2113 2414, 2314, 2214, 2114 2415, 2315, 2215, 2115 2416, 2316, 2216, 2116 |
6/11/18 – 6/15/18 8am |
2417, 2317, 2217, 2117 2418, 2318, 2218, 2118 2419, 2319, 2219, 2119 2420, 2320, 2220, 2120 |
6/18/18 – 6/22/18 8am |
2421, 2321, 2221, 2121 2422, 2322, 2222, 2122 2423, 2323, 2223, 2123 2424, 2324, 2224, 2124 |
6/25/18 – 6/29/18 8am |
Building 3 – 7/9/18 to 8/10/18
3409, 3309, 3209, 3109 |
7/9/18 – 7/13/18 8am |
3413, 3313, 3213, 3113 |
7/16/18 – 7/20/18 8am |
3401, 3301, 3201, 3101 |
7/23/18 – 7/27/18 8am |
3405, 3305, 3205, 3105 |
8/6/18 – 8/10/18 8am |
3417, 3317, 3217, 3117 |
8/13/18 – 8/17/18 8am |
3421, 3321, 3221, 3121 |
8/20/18 – 8/24/18 8am |
Attention Owners
- 4 stacks will be worked on at the same time
- Schedule is established and cannot be negotiated
- Owners, guests, LT Tenants – NO Occupancy
- Notification will be posted on our website
- Work will take 5 days and no unit can be occupied
- Water off, pipes disconnected during 5-day period
- No water can be in lines due to disconnections
- Owners and Agents reminded the week before